B&Q, Livingston

We were delighted to hand over this 'new' B&Q store, just a short distance from our regional office in Livingston.

Overview

Client:

B&Q

Location:

Livingston

Project:

New Store Fit Out

Value:

Duration:

8 Weeks

The Brief

The project involved the strip out and fit out of a vacant portal unit of the original B&Q store, which closed in 2016, including full external enhancements.

The Scope

  • Carried out the taking down of fixture and fittings including redundant M&E along with uplifting of existing floor coverings.
  • Prepared and finished the concrete floor with a polishing system.
  • Installed new racking storage systems.
  • Installed and upgraded staff toilets, welfare area and created new office, cleaners store and disabled toilet.
  • Supplied and installed new sliding entrance doors along with internal sliding doors to builders’ yard and garden centre.
  • General repairs to existing perimeter fencing and security gates.
  • Complete new installation of light fittings, small power, and PA System.
  • Installed new section of sprinklers to welfare areas.
  • Installed completely new IT installation by Kingfisher along with ADT intruder alarms.
  • Supplied and installed new cash checkouts and showroom displays.
  • General decoration to the store including internal doors etc.
  • Shop fitting installation of new displays and Valspar paint shop.
  • Formation of Goods Inward area with fast-track door and new Load & Go area including new roller shutter within newly formed opening.
  • New Tarmac and road markings for customer parking and safe walkways within the service yard.
  • Image installation of new signage including B&Q marketing POS within the store.
  • External respray of the store to specification.

The Results

The site team carried out an exceptional job and we had great support from the B&Q teams whilst, building good relationships during the project. A real team effort.